Yes, what you say is completly valid. My issue is after the production is done. 

Current behaviour is that the works are in 'finished'. But the _state is 'done' when the production is finished. 

The problem is that the work state is never updated when the production is done, so all the works are still in finished state which allows the user to create a new cycle for them (which for me is not correct). Then the work is state is updated to done but there is an active cycle on it. 

So I think the right behaviour is to set all the works to done once the production is done and do not allow to create new cycles.
History
Date User Action Args
2020-06-15 16:41:54pokolisetmessageid: <1592232114.13.0.729387029733.issue9417@tryton.org>
2020-06-15 16:41:54pokolisetrecipients: + ced, reviewbot
2020-06-15 16:41:54pokolilinkissue9417 messages
2020-06-15 16:41:53pokolicreate

Showing 10 items. Show all history (warning: this could be VERY long)